Mangistauenergomunai LLP was founded on 25 January 1995 and has been a wholly owned subsidiary of NC KazMunayGas JSC since 23 December 2016. The partnership is a diversified company in the power industry.
About the company
The partnership was established on 25 January 1995 on the basis of the electrical shop (PRTsEO) of the Komsomolskneft oil and gas production department and the PTS-4 unit of the Uzenenergoneft production department.
In 1998 the scope of operations expanded: the Zhetybai site became part of the partnership. Since 23 December 2016 the company has been a wholly owned first-tier subsidiary of KazMunayGas.
Its core business is supplying electricity to consumers, maintaining the electrical networks at the Kalamkas and Zhetybai fields and running the 2×45 MW gas turbine power plant at Kalamkas. The plant is owned by Mangistaumunaigas: the partnership is responsible for its technical operation and is not a power-generating organisation. The 2017–2018 transformation made the partnership one of the country's major oilfield service companies.
Key dates
1995
The Kalamkasenergomunai production department is converted into Mangistauenergomunai LLP.
1998
Operations expand: the Zhetybai site becomes part of the partnership.
2000–2005
On the company's initiative and under its technical supervision, the 2×45 MW gas turbine power plant is built at the Kalamkas field.
2014
The 2×45 MW gas turbine power plant is commissioned; the company takes on its technical operation and becomes a participant in the electricity market of Kazakhstan.
2016
The company becomes a wholly owned first-tier subsidiary of KazMunayGas.
2017–2018
Digitalisation of power distribution systems (SCADA, remote control and telemetry); the transformation that turned the company into a major oilfield service business.
2019
On the company's proposal, variable-frequency control stations for well pumps are introduced for the first time — 404 units.
2020
Integration of an automated commercial and technical electricity metering system: 2,916 meters for Mangistaumunaigas and 934 for Ozenmunaigas.
2022
Variable-frequency drives with automated control are introduced: five 6 kV 1,650 kW booster pumps in cascade mode and 124 group-unit pumps of 90 kW.
2023–2024
Construction of national importance: engineering and utility infrastructure for the Tokymak seawater desalination plant — an 83 km 110 kV overhead line and two 110/10 kV substations; upgrade and reconstruction of the 220/110/10 kV Uzen substation of MREK.
2024–2025
The first company in Kazakhstan and the 205th in the world certified to the API Spec Q2 specification.
What we do
01
Supplying electricity to consumers.
02
Maintenance and repair of electrical networks and installations.
03
Technical operation of the 2×45 MW gas turbine power plant at the Kalamkas field.
04
Commissioning, testing and measurement of electrical installations, automation and protection systems.
05
Overhaul, reconstruction and upgrade of electrical installations and distribution networks.
06
Construction of power supply facilities and installations rated up to 110 kV, including commissioning works.
Our strengths
The partnership offers its clients and partners a combination of operational reliability, the backing of a national company and compliance with international standards.
Reliability and stability
A financially sound company and a first-tier subsidiary of NC KazMunayGas JSC.
Professional expertise
Experience across a wide range of services and works: operation, construction, overhaul, reconstruction and upgrade of electrical installations, and operation of gas-turbine power generation facilities.
Qualified staff
A qualified engineering and technical team.
Advanced technology
Use of advanced equipment from Siemens, Schneider Electric, ABB and other manufacturers.
Safety
Strict adherence to safety rules at the level of international companies: 2,864 days without injuries.
Management systems
The company's operations meet international standards for quality, environmental management, energy management and occupational safety. In 2024 it became the first and so far the only company in Kazakhstan to hold the API Spec Q2 certificate.
ISO 9001:2015 — quality management system
ISO 14001:2015 — environmental management system
ISO 45001:2018 — occupational health and safety system
ISO 50001:2018 — energy management system
API Spec Q2 — service quality in the oil and gas industry
ST RK ISO 37001-2025 — anti-bribery management system



API Spec Q2, second edition
In 2022 the requirements of API Spec Q2 (second edition), the quality management system for service suppliers to the oil and gas industry, were built into the company's management system. In 2023 it completed two stages of the initial certification audit by the American Petroleum Institute. In 2024 the partnership became the first — and to date the only — company in Kazakhstan to pass every stage of the audit and receive the API Spec Q2 certificate of conformity.
Permits and licences
The company holds permits for the construction of power facilities, including category 1 construction and installation works, as well as a certificate authorising the maintenance of gas-consuming systems in the oil and gas, petrochemical and power industries.